Part of the Network operations domain, which makes up ~22% of our current practice bank. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~8–13 in this domain), expect 1–2 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
9concepts
Questions 6–10
- 6
A company's risk assessment identifies that a power outage at the primary data center could last up to 8 hours. The company's RTO for its CRM system is 4 hours. The current DR plan relies on a backup generator that only has fuel for 2 hours. Which option best addresses this risk while considering cost?
Select an answer first - 7
During a major network outage, a company's DR team needs to inform employees, customers, and the executive team. The communication plan currently lists only the IT manager's personal email as the primary contact method. Which improvement best strengthens the communication plan?
Select an answer first - 8
What is the purpose of redundancy in network design?
Select an answer first - 9
A university's network team is conducting a risk assessment. They identify that a single fiber cut could disconnect the entire campus from the internet because all uplinks leave the building through one conduit. Which mitigation directly addresses this risk?
Select an answer first - 10
What is the purpose of a risk assessment in network operations?
Select an answer first