Questions 21–25
- 21
A project manager is implementing best practices for materials management on a project that involves both perishable and non-perishable materials. The project manager wants to ensure that perishable materials are used before they expire. What is the most effective practice?
Select an answer first - 22
What is the critical path in a project schedule?
Select an answer first - 23
A project manager is estimating the quantity of rebar needed for a concrete structure. The design drawings specify the rebar sizes and spacing, but there is a 5% allowance for waste and off-cuts. The project manager wants to ensure the budget is accurate. Which estimation method is most appropriate?
Select an answer first - 24
A project manager is implementing a materials management process for a new building project. The team has completed the strategy and planning phase and is about to place orders for key materials. Which sequence of activities best reflects the end-to-end materials management process?
Select an answer first - 25
A project manager is planning the delivery of large prefabricated wall panels to a construction site. The panels are manufactured off-site and must be delivered in a specific sequence to match the installation schedule. The site has limited storage space. What is the most effective delivery plan?
Select an answer first