Questions 21–25
- 21
During the construction phase of a hospital project, the project manager receives a shipment of 500 boxes of ceramic tile. The packing slip indicates 500 boxes, but a quick visual inspection reveals that several boxes appear damaged. What should the project manager do first?
Select an answer first - 22
What is the first step when damaged goods are received?
Select an answer first - 23
A project manager is planning the waste management for a large industrial plant construction. The project will generate significant amounts of scrap metal, packaging waste, and hazardous waste (e.g., solvents). The project manager wants to minimize environmental impact and disposal costs. Which waste management plan is most appropriate?
Select an answer first - 24
A project manager is procuring lumber for a residential development. The project requires 50,000 board feet over the next year. The supplier offers a 10% discount for orders of 20,000 board feet or more. The project has limited on-site storage, and lumber is susceptible to weather damage. What is the most appropriate procurement strategy?
Select an answer first - 25
What is a key benefit of aligning material procurement with the project schedule?
Select an answer first