  1. 31application · medium

    A private developer is building a mixed-use tower. They want to minimize their own administrative burden and avoid disputes over change orders. They are willing to pay a premium for certainty. Which contract structure is most appropriate?

    Select an answer first
  2. 32expert · hard

    A developer is comparing design-bid-build and design-build for a new office building. They are concerned about the risk of cost overruns and want to know which method gives them more cost certainty. They also want to maintain some control over the design. What is the most accurate advice?

    Select an answer first
  3. 33foundation · easy

    In a built environment contract, which clause is designed to address unforeseen conditions such as contaminated soil or hidden utilities?

    Select an answer first
  4. 34application · medium

    A public agency is procuring a new courthouse. The design is 60% complete and the agency wants to bring the contractor on board early to provide constructability input and to share risk on cost overruns. They also want a single point of responsibility for the completed facility. Which delivery method and contract structure best meets these needs?

    Select an answer first
Finished these 4 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to PMI-CP

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-CP” is a trademark of its owner, used for identification only.