Questions 31–34
- 31
Which risk classification would a risk of a new environmental regulation affecting a construction project fall under?
Select an answer first - 32
Which tool is commonly used to visually display risks based on their likelihood and impact?
Select an answer first - 33
What is the purpose of assessing the impact of technology decisions on a construction project?
Select an answer first - 34
A project is using a cloud-based collaboration platform that the client's security team has flagged as non-compliant with their data residency requirements. The project manager must decide whether to switch platforms mid-project. The switch will cause a two-week delay and require retraining. What is the most appropriate decision-making approach?
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-CP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-CP” is a trademark of its owner, used for identification only.