Questions 6–10
- 6
A project manager is staffing a PRiSM project to develop a sustainable water treatment plant. The project requires specialized environmental expertise. Which staffing decision best aligns with PRiSM principles?
Select an answer first - 7
What is the purpose of including sustainability milestones in the project schedule?
Select an answer first - 8
A project manager is budgeting for a PRiSM project to build a sustainable community center. The project has a fixed budget. Which cost control measure best aligns with PRiSM's sustainable financial practices?
Select an answer first - 9
In a PRiSM project, which management plan would specify how to select suppliers that meet sustainability criteria?
Select an answer first - 10
A project manager is managing the finances of a PRiSM project to build a sustainable office building. The project has a fixed budget and a goal to minimize waste. Which financial practice best aligns with PRiSM?
Select an answer first