Part of the Why Have a P3O? domain, which makes up ~38% of our current practice bank. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~23–38 in this domain), expect 6–10 from this objective — we provide 40 practice questions to prepare you well beyond it. (estimate)
40questions here
8free pages
12concepts
Questions 26–30
- 26
Why should the implementation of a P3O be planned as a project or business change programme?
Select an answer first - 27
A public-sector organization is designing a new P3O. The Head of P3O is identifying stakeholders for the service catalogue. Which stakeholder group would have the most direct interest in the 'independent assurance of projects' service?
Select an answer first - 28
Which cost model is most commonly associated with a temporary P3O?
Select an answer first - 29
A pharmaceutical company is establishing a P3O to improve the success rate of its R&D projects. The P3O lead is defining the capabilities the P3O will need. Which capability is most directly linked to the outcome of 'improved project success rate'?
Select an answer first - 30
Which method is commonly used to identify key problems that a P3O could address?
Select an answer first