Know Facts, Terms and Concepts Relating to Selecting the Right P3O Model and Its Functions and Services. Specifically to Recall: P3O-FOUNDATION Practice Questions (Page 3)
Part of the Models and Tailoring domain, which makes up ~34% of our current practice bank. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~9–14 in this domain), expect 2–4 from this objective — we provide 14 practice questions to prepare you well beyond it. (estimate)
14questions here
3free pages
2concepts
Questions 11–14
- 11
A healthcare organization has a permanent Portfolio Office that oversees all change initiatives. The organization is launching a 4-year electronic health records program that will be delivered in phases. Each phase has its own go-live date and requires dedicated support. The Portfolio Office is at capacity. The organization has a limited budget and must decide between one large temporary Programme Office for the whole program or a series of smaller temporary offices for each phase. What is the most appropriate P3O design?
Select an answer first - 12
A utility company has a permanent Portfolio Office that manages a large, ongoing portfolio of infrastructure projects. The company is bidding for a 3-year government contract to upgrade a regional power grid. The contract, if won, would be managed as a single program with its own reporting requirements to the government. What should the company do to prepare for the program's P3O support?
Select an answer first - 13
Which type of P3O office is established to support a specific change initiative and is typically disbanded once that initiative is completed?
Select an answer first - 14
A technology company has a permanent Project Support Office (PSO) that provides administrative support to all projects. The company is launching a 2-year cloud migration program. The program needs dedicated support for dependency management and benefits tracking. The PSO has capacity but its staff are generalists. The company has a limited budget and must choose between hiring specialists for the program or training the PSO staff. Training would take 3 months but would upskill the PSO for future programs. The program's benefits tracking is not needed until month 6. What is the most appropriate P3O decision?
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.