Part of the Models and Tailoring domain, which makes up ~34% of our current practice bank. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~9–14 in this domain), expect 2–4 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)
28questions here
6free pages
6concepts
Questions 21–25
- 21
A temporary programme office is being set up for a two-year programme. The programme is small, with only three projects, but it is strategically important. The organization wants to keep costs low. What is the most appropriate size for the programme office?
Select an answer first - 22
A P3O provides portfolio management, programme management, and project management support. The portfolio office has identified that several projects are duplicating effort and competing for the same limited resources. The programme office is managing a programme that includes two of these projects. What should the P3O do to address the duplication and resource contention?
Select an answer first - 23
An organization is restructuring its P3O. Currently, it has a single office that supports both portfolio and programme management. The organization has grown and now has a large portfolio of diverse programmes and projects. The P3O manager is considering splitting the office into a permanent portfolio office and temporary programme offices. What is the most important factor to consider in this decision?
Select an answer first - 24
Which P3O structure is typically responsible for providing support to individual projects, such as planning, reporting, and risk management?
Select an answer first - 25
A multinational company is establishing a permanent P3O to support its portfolio of strategic change. The CEO has publicly endorsed the P3O and allocated a dedicated budget, but the heads of the business units are reluctant to share their project and programme information with the new office. The P3O manager is concerned that without their cooperation, the P3O will not be able to provide reliable portfolio-level reporting. What should the P3O manager do first?
Select an answer first