Understand the Terms and Concepts Relating to the Portfolio Definition Cycle MOP-PRACTITIONER Practice Questions (Page 9)
Part of the Portfolio definition cycle domain, which makes up ~23% of our current practice bank.
41questions here
9free pages
11concepts
Questions 41–41
- 41
A software company is deciding whether to include a high-risk platform migration in its portfolio. The project manager provides an optimistic estimate of 6 months, a pessimistic estimate of 18 months, and a most likely estimate of 12 months. The portfolio office needs a single expected duration to use in the portfolio's capacity plan. Which technique should they apply?
Select an answer first
Finished these 1 questions?
Review the revealed explanations, or continue through the curriculum.