Part of the Plan and implement data platform resources domain, which accounts for 15–20% of the DP-300 exam. Microsoft does not publish an official question count, but from its 100-minute exam (~40–65 total, ~6–13 in this domain), expect 2–4 from this objective — we provide 40 practice questions to prepare you well beyond it. (estimate)
40questions here
8free pages
9concepts
15–20%of the exam
Questions 31–35
- 31
A company is planning to migrate its on-premises SQL Server databases to Azure SQL Database. During the requirements evaluation phase, which two categories of requirements must be assessed to define the migration strategy?
Select an answer first - 32
A company is migrating a 1-TB database from Azure SQL Managed Instance to Azure SQL Database. The application requires a specific compatibility level that is supported by both services. The migration must minimize downtime, but the company has a limited budget and cannot afford a long-running online migration. What is the best approach?
Select an answer first - 33
Which scenario is best suited for an offline database migration strategy?
Select an answer first - 34
A manufacturing company is migrating a 10-TB data warehouse to Azure SQL Database. The business has approved a 12-hour downtime window over the weekend. The network link to Azure is 100 Mbps. What is the most important consideration when planning the offline migration?
Select an answer first - 35
What is the primary benefit of an online migration strategy compared to an offline migration?
Select an answer first