Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
ISTQB logo

Certified Tester Expert Level Test Management Operational Test Management

Domain 3Objective 6

Implementation and Execution CTEL-TM-OTM Practice Questions (Page 2)

Part of the Test Project Evaluation and Reporting domain, which makes up ~47% of our current practice bank.

27questions here
6free pages
7concepts

Questions 6–10

  1. 6application · medium

    A test manager is planning the execution phase for a project that requires a specific version of a third-party application. The environment team says the application will be available two weeks after the planned start of execution. The test manager needs to adjust the test implementation plan. What is the best course of action?

    Select an answer first
  2. 7expert · hard

    A test manager is leading a test phase where the test environment is frequently unavailable, causing many tests to be blocked. The test manager has already reordered the test schedule and added buffer time, but the environment issues persist. What is the next best step?

    Select an answer first
  3. 8foundation · easy

    What is documented when test completion is assessed?

    Select an answer first
  4. 9foundation · easy

    Which activity is primarily part of test implementation planning during the execution phase?

    Select an answer first
  5. 10application · medium

    During test execution, a tester finds a defect that is not in the scope of the current release but is a known issue in the legacy system. The defect management process requires that all defects be logged. What should the test manager instruct the tester to do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by ISTQB. “CTEL-TM-OTM” is a trademark of its owner, used for identification only.