Questions 6–10
- 6
A test manager is planning the execution phase for a project that requires a specific version of a third-party application. The environment team says the application will be available two weeks after the planned start of execution. The test manager needs to adjust the test implementation plan. What is the best course of action?
Select an answer first - 7
A test manager is leading a test phase where the test environment is frequently unavailable, causing many tests to be blocked. The test manager has already reordered the test schedule and added buffer time, but the environment issues persist. What is the next best step?
Select an answer first - 8
What is documented when test completion is assessed?
Select an answer first - 9
Which activity is primarily part of test implementation planning during the execution phase?
Select an answer first - 10
During test execution, a tester finds a defect that is not in the scope of the current release but is a known issue in the legacy system. The defect management process requires that all defects be logged. What should the test manager instruct the tester to do?
Select an answer first