Questions 11–15
- 11
Which of the following is a quantitative data collection method for test project evaluation?
Select an answer first - 12
A test manager is evaluating a test project and wants to understand why the number of defects found in the system test phase was lower than expected. The team suspects that testers may have missed defects due to time pressure. Which data collection method is most appropriate to gather qualitative insights into this issue?
Select an answer first - 13
What is the main purpose of formulating recommendations based on test evaluation results?
Select an answer first - 14
Which of the following is the primary purpose of defining evaluation criteria during test project evaluation planning?
Select an answer first - 15
In a test project evaluation, the test manager observes that the number of defects found per test execution cycle is decreasing over time, but the number of high-severity defects remains constant. The team believes this indicates the system is stabilizing. The test manager is not convinced and wants to analyze the data more deeply. What should the test manager do?
Select an answer first