Performance Risks Across the Software Development Lifecycle CT-PT Practice Questions (Page 5)

Part of the Performance Testing in the Software Lifecycle domain, which makes up ~19% of our current practice bank. ISTQB does not publish an official question count, but from its 90-minute exam (~35–60 total, ~7–11 in this domain), expect 2–3 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)

27questions here
6free pages
4concepts

Questions 21–25

  1. 21application · medium

    A team is developing a mobile app that syncs data with a backend server. During the design phase, they identify a risk that the sync process may consume excessive battery and data on mobile devices. Which mitigation strategy is most appropriate?

    Select an answer first
  2. 22application · medium

    During the design phase, the architecture team proposes using a single relational database for both transactional and reporting workloads. The performance test lead is asked to identify potential performance risks. Which risk is most likely to arise from this design?

    Select an answer first
  3. 23application · medium

    A team is developing a real-time chat application. During the design phase, they identify a risk that the WebSocket connections may not scale to support the expected number of concurrent users. Which mitigation strategy is most appropriate?

    Select an answer first
  4. 24foundation · easy

    A project team decides to use a new caching framework during the design phase. Which performance risk is most directly associated with this decision?

    Select an answer first
  5. 25application · medium

    A team is starting a new web application project. During the requirements phase, they document that the system must support 500 concurrent users during peak hours, but they do not specify any performance targets for response times or resource utilization. The project manager wants to avoid performance issues later. What is the most effective action to take during this phase?

    Select an answer first