Part of the Basic Concepts domain, which makes up ~25% of our current practice bank. ISTQB does not publish an official question count, but from its 90-minute exam (~35–60 total, ~9–15 in this domain), expect 2–3 from this objective — we provide 18 practice questions to prepare you well beyond it. (estimate)
18questions here
4free pages
3concepts
Questions 11–15
- 11
A team is testing a new online payment system. They have a test environment that is a scaled-down version of production, with half the CPU and memory. The team has run functional tests successfully, but performance tests show response times that are 3 times higher than expected. The business owner is concerned that the system will not meet performance targets in production. Which action is most appropriate?
Select an answer first - 12
A performance test team is preparing to validate a new e-commerce checkout service. They have a test script that sends HTTP requests, but they have not yet executed it against the running application. The team lead insists that the script must be run against the deployed build before any performance metrics can be reported. Which statement best explains why the team lead's requirement is correct?
Select an answer first - 13
A test team is working on a legacy system that has no automated test infrastructure. They need to validate a new feature that calculates shipping costs based on weight and destination. The team has a running instance of the application and a list of test cases. Which approach best applies dynamic testing in this context?
Select an answer first - 14
A performance test team is preparing to test a new online streaming service. The service is expected to have a baseline load of 1,000 concurrent users and a peak load of 5,000 concurrent users during major events. The team has a limited test window of 4 hours. They need to validate both functional correctness and performance under these loads. Which approach best balances the need for functional validation and performance measurement within the time constraint?
Select an answer first - 15
How is dynamic testing applied in performance testing?
Select an answer first