Questions 26–30

  1. 26foundation · easy

    Story mapping is a release planning technique that helps the team:

    Select an answer first
  2. 27application · medium

    After a release planning session, the product owner wants to share the plan with stakeholders. What should the release plan include to be most useful?

    Select an answer first
  3. 28foundation · easy

    Which of the following is a key input to release planning in agile?

    Select an answer first
  4. 29foundation · easy

    Iteration planning in agile is primarily focused on:

    Select an answer first
  5. 30expert · hard

    A team has a capacity of 40 story points for the next iteration. The product owner wants to include a high-priority feature worth 30 points and a medium-priority feature worth 15 points. The team's historical completion rate is 85%. Which iteration backlog should the team commit to?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by ISTQB. “CT-AT” is a trademark of its owner, used for identification only.