Part of the Security Program Management and Operations domain, which makes up ~17% of our current practice bank. EC-Council does not publish an official question count, but from its 120-minute exam (~50–80 total, ~9–14 in this domain), expect 2–4 from this objective — we provide 55 practice questions to prepare you well beyond it. (estimate)

55questions here
11free pages
9concepts

Questions 26–30

  1. 26expert · hard

    A security program manager is reporting to the board on a security awareness project. The board wants to understand the project's impact on reducing human-related security incidents. Which reporting approach would be most effective?

    Select an answer first
  2. 27application · medium

    During the execution of a security awareness training project, the project manager notices that the completion rate for mandatory training modules is significantly below the target. What is the most appropriate control action?

    Select an answer first
  3. 28application · medium

    A regional bank is planning a multi-year rollout of a new customer authentication platform. The project sponsor has mandated a fixed go-live date because of regulatory deadlines, but the security team has identified that the current vendor integration timeline is uncertain. The project manager must develop a plan that balances the fixed date with the security team's concerns. Which approach best addresses this constraint?

    Select an answer first
  4. 29expert · hard

    A security project to implement a new vulnerability management program is in its execution phase. The project manager must report to the steering committee, which includes executives who are not technical. Which set of metrics would be most effective for this audience?

    Select an answer first
  5. 30application · medium

    A security project to implement a new identity management system is experiencing delays. The project manager needs to inform stakeholders and decide on corrective action. Which governance mechanism should be used to address the delay?

    Select an answer first