Objective 1.1 Identify the Project Scope CERTIFIED-DATA-SCIENCE-PRACTITIONER Practice Questions (Page 3)
Part of the 1.0 Defining the need to be addressed through the application of data science domain, which accounts for 7-9% of the CERTIFIED-DATA-SCIENCE-PRACTITIONER exam.
22questions here
5free pages
4concepts
7-9%of the exam
Questions 11–15
- 11
A retail company wants to build a churn prediction model to reduce customer attrition. The business sponsor states that the model must be deployed by the end of the quarter to meet a regulatory deadline, but the data engineering team has not yet consolidated the required customer transaction data. The data science team is asked to define the project specifications. Which approach best aligns the project scope with stakeholder expectations?
Select an answer first - 12
A government agency is building a model to predict traffic congestion. The project has a fixed deadline of 3 months because the model must be used in an upcoming city planning review. The team has identified that the required traffic sensor data is only available from a third-party vendor, and the vendor has a history of delayed deliveries. What should the project manager do to manage the timeline effectively?
Select an answer first - 13
A healthcare analytics company is building a model to predict patient no-shows. The project has a strict deadline of 6 weeks. The team has access to historical appointment data, but it is stored in a legacy system that requires manual export, which takes 2 weeks. The team also needs to comply with data privacy regulations, which require de-identification of patient data. The project sponsor wants the model to be deployed in the clinic's scheduling system. Which combination of limitations is most critical to address in the project plan?
Select an answer first - 14
A transportation company is building a model to predict delivery delays. The project has a fixed deadline of 2 months. The team has identified that the required weather data is available from a public API, but the API has rate limits that could slow down data collection. The team also needs to integrate the model with the company's routing system, which is managed by another team. The project manager must create a timeline. What is the best approach?
Select an answer first - 15
Which of the following is an example of a technical constraint that could limit a data science project?
Select an answer first